[Construction Case] Slab Foundation House: Settlement Correction Work (Tokyo)

No need for large-scale demolition work! Here is an example of correcting a settlement of up to 95mm in just two days of construction.

We would like to introduce a case of "settlement repair work" carried out on a slab foundation house located in Hachioji City, Tokyo. Due to a maximum settlement of 95mm observed, polyurethane resin was injected under the slab foundation to implement the settlement correction. If you are troubled by the tilting of your slab foundation house caused by earthquakes, liquefaction, or ground subsidence, please feel free to contact us. 【Case Overview】 ■ Construction Area: Approximately 43m2 ■ Maximum Settlement: 95mm ■ Area: Hachioji City, Tokyo ■ Construction Period: 2 days *For more details, please refer to the PDF materials or feel free to contact us.

  • Renovation and repair methods
  • Ground foundation construction method
  • Special Construction Method

Added to bookmarks

Bookmarks list

Bookmark has been removed

Bookmarks list

You can't add any more bookmarks

By registering as a member, you can increase the number of bookmarks you can save and organize them with labels.

Free membership registration

[Construction Case] Slab Foundation House: Settlement Correction Work (Tottori Prefecture)

No need for large-scale demolition work! Here are examples of cases where a settlement of up to 46mm was corrected.

We would like to introduce a case of "settlement correction work" carried out on a slab foundation house in Unnan City, Tottori Prefecture. Since a maximum settlement of 46mm was observed, resin was injected under the slab foundation to implement the correction. Our company was chosen because the correction could be made without large-scale demolition work or moving. 【Case Overview】 ■ Construction Area: Approximately 106m2 ■ Maximum Settlement Amount: 46mm ■ Area: Unnan City, Tottori Prefecture ■ Construction Period: 2 days *For more details, please refer to the PDF document or feel free to contact us.

  • Renovation and repair methods
  • Ground foundation construction method
  • Civil Engineering Method

Added to bookmarks

Bookmarks list

Bookmark has been removed

Bookmarks list

You can't add any more bookmarks

By registering as a member, you can increase the number of bookmarks you can save and organize them with labels.

Free membership registration